RAB
ESTIMASI :
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : RELOKASI TEMPAT IBADAH, MESJID AL-AMIN, PEDAK
LOKASI : PEDAK, SINDUHARJO, NGAGLIK, SLEMAN, YOGYAKARTA
TAHUN ANGGARAN : 2013
NO URAIAN PEKERJAAN VOLUME SAT NO. ANALISA HARGASATUAN JUMLAH HARGA KOMULATIF SUB
(Rp.) (Rp.) (Rp.)
A. LINGKUP PEKERJAAN LANTAI-1
A.I. PEKERJAAN PERSIAPAN
1 Pengukuran, Uitzet / bouwplank 267,00 m' LS 12.500,00 3.337.500,00
2 Administrasi & dokumentasi 1,00 unit LS 750.000,00 750.000,00
3 Air kerja dan Listrik kerja 1,00 unit LS 1.500.000,00 1.500.000,00
4 Direksi keet 20,00 m2 LS 150.000,00 3.000.000,00
5 Pembersihan Lokasi 364,00 m2 LS 8.500,00 3.094.000,00
JUMLAH A. I 11.681.500,00 11.681.500,00
A.II. PEKERJAAN STRUKTUR
a. PEKERJAAN TANAH
1 Galian tanah pondasi batu+footplat kedalaman max 2,5 m 204,93 m3 SNI-2835-2008 6.3 51.940,00 10.643.804,50
2 Urugan tanah kembali bekas galian 124,15 m3 SNI-2835-2008 6.9 11.821,50 1.467.662,87
3 Urugan pasir bawah pondasi 11,75 m3 SNI-2835-2008 6.11 80.200,00 942.350,00
4 Urugan Tanah Peninggian Elevasi Bangunan+Meratakan 320,35 m3 SNI-2835-2008 6.15 90.250,00 28.911.407,00
JUMLAH A.II.a 41.965.224,37 53.646.724,37
b. PEKERJAAN PASANGAN di LANTAI 1
1 Pasang Pondasi batu kali camp 1 PC : 5 PS 50,00 m3 SNI-2836-2008. 6.3 440.725,00 22.036.250,00
2 Pasangan Bata 1/2 Batu, camp. 1Pc : 5 Ps 329,79 m2 SNI-6897-2008. 6.10 90.259,00 29.766.515,61
3 Plesteran Dinding camp. 1Pc : 5 Ps 899,58 m2 SNI-2837-2008. 6.5 33.785,00 30.392.310,30
4 Plesteran Beton camp. 1 Pc : 3 Ps 92,40 m2 SNI-2837-2008. 6.3 37.238,00 3.440.791,20
5 Pekerjaan Acian Dinding dan Beton 1.419,67 m2 SNI-2837-2008. 6.27 21.162,00 30.043.077,70
6 Pekerjaan Sponengan Sudut 1.826,16 m' SNI-2837-2008. 6.20 8.695,00 15.878.461,20
7 Pasangan Dinding rooster beton, ukuran 20x20 82,77 m2 Taksir 275.000,00 22.761.750,00
JUMLAH A.II.b 154.319.156,01 207.965.880,38
c. PEKERJAAN BETON di LANTAI - 1
1 Cor Beton Lantai Kerja
Beton mutu fc=14,5 Mpa(K175), slump (12 ± 2)cm, w/c= 0,66 2,42 m3 SNI-7394-2008. 6.5 831.510,00 2.015.580,24
2 Cor Beton Foot Plate 150x150x25 dan 100x100x25
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 10,92 m3 SNI-7394-2008. 6.8 903.815,00 9.869.659,80
b Pembesian Foot Plate 150x150 1.373,76 kg SNI-7394-2008. 6.17 10.720,50 14.727.439,23
c Begesting Foot Plate 150x150, 2 x pakai 45,00 m2 SNI-7394-2008. 6.20 27.255,00 1.226.475,00
3 Cor Beton Pedestal 30x30 dan 20x20
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 5,78 m3 SNI-7394-2008. 6.8 903.815,00 5.224.954,52
b Pembesian Pedestal 30X30 dan 20X20 682,82 kg SNI-7394-2008. 6.17 10.720,50 7.320.178,29
c Begesting Pedestal , 2 x pakai 54,00 m2 SNI-7394-2008. 6.20 27.255,00 1.471.770,00
4 Cor Beton Sloof 20x30
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 14,12 m3 SNI-7394-2008 6.5 903.815,00 12.757.348,73
b Pembesian Sloof 20/30 2.593,75 kg SNI-7394-2008 6.17 10.720,50 27.806.249,51
c Begesting Sloof 2 x pakai 141,15 m2 SNI-7394-2008 6.21 21.210,00 2.993.791,50
5 Cor Beton kolom struktur K1 30x30
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 7,43 m3 SNI-7394-2008 6.8 903.815,00 6.710.826,38
b Pembesian kolom 1.184,00 kg SNI-7394-2008 6.17 10.720,50 12.693.025,34
c Begesting kolom 2 x pakai 105,60 m2 SNI-7394-2008 6.22 43.922,50 4.638.216,00
6 Cor Beton kolom struktur K2 20x20
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 2,88 m3 SNI-7394-2008 6.8 903.815,00 2.602.987,20
b Pembesian kolom 451,65 kg SNI-7394-2008 6.17 10.720,50 4.841.891,31
c Begesting kolom 2 x pakai 57,60 m2 SNI-7394-2008 6.22 43.922,50 2.529.936,00
7 Cor Beton balok struktur B1 30x40
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 14,90 m3 SNI-7394-2008.6.8 903.815,00 13.470.458,76
b Pembesian Balok 2.130,18 kg SNI-7394-2008 6.17 10.720,50 22.836.627,70
c Begesting Balok 2 x pakai 117,30 m2 SNI-7394-2008.6.23a 87.845,00 10.304.569,88
8 Cor Beton balok struktur B2 15x30
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 1,62 m3 SNI-7394-2008.6.8 903.815,00 1.464.180,30
b Pembesian Balok 356,92 kg SNI-7394-2008 6.17 10.720,50 3.826.402,76
c Begesting Balok 2 x pakai 18,36 m2 SNI-7394-2008.6.23a 131.767,50 2.419.251,30
9 Cor Beton Plat Lantai-2/Dag, tebal 12 cm
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 23,76 m3 SNI-7394-2008.6.8 903.815,00 21.474.644,40
b Pembesian Plat Lantai 3.650,07 kg SNI-7394-2008 6.17 10.720,50 39.130.624,32
c Begesting Plat Lantai 2 x pakai 134,56 m2 SNI-7394-2008.6.24a 161.767,50 21.767.434,80
10 Cor Beton Luisplank Lantai-1, 10x50
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 2,30 m3 SNI-7394-2008.6.8 903.815,00 2.078.774,50
b Pembesian Luisplank 399,29 kg SNI-7394-2008 6.17 10.720,50 4.280.639,05
c Begesting Luisplank 2 x pakai 46,00 m2 SNI-7394-2008.6.24a 161.767,50 7.441.305,00
11 Cor Beton Tangga 2 (dua) unit di sayap utara+selatan
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 14,32 m3 SNI-7394-2008.6.8 903.815,00 12.946.133,08
b Pembesian Plat + Anak tangga 512,68 kg SNI-7394-2008 6.17 10.720,50 5.496.200,95
c Begesting Plat+Anak Tangga 2 x pakai 18,90 m2 SNI-7394-2008.6.24a 161.767,50 3.057.405,75
12 Cor Beton Balok Latae 15x20
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 3,62 m3 SNI-7394-2008. 6.8 903.815,00 3.268.375,80
b Pembesian Balok Latae 459,11 kg SNI-7394-2008 6.17 10.720,50 4.921.836,85
c Begesting Balok 2 x pakai 66,30 m2 SNI-7394-2008.6.23a 131.767,50 8.735.789,95
13 Cor Beton Kolom Praktis 15x20
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 3,83 m3 SNI-7394-2008. 6.8 903.815,00 3.457.092,38
b Pembesian Kolom Praktis 4,73 kg SNI-7394-2008 6.17 10.720,50 50.758,57
c Begesting Kolom Praktis 2 x pakai 51,00 m2 SNI-7394-2008 6.22 65.883,75 3.360.071,25
14 Cor Beton Plat canopy (assesories diatas Jendela)
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 0,64 m3 SNI-7394-2008. 6.8 903.815,00 578.441,60
b Pembesian Plat canopy 138,89 kg SNI-7394-2008 6.17 10.720,50 1.488.917,93
c Begesting Plat canopy 2 x pakai 16,00 m2 SNI-7394-2008.6.24a 161.767,50 2.588.280,00
JUMLAH A.II.c 291.424.981,58 499.390.861,96
A.III. PEKERJAAN PASANGAN ARSITEKTURAL LANTAI 1
a. PEKERJAAN LANTAI di LANTAI-1
1 Urugan Pasir Bawah Lantai, Tebal 7 cm 15,59 m3 SNI-2835-2008. 6.11 80.200,00 1.250.350,08
2 Cor Rabat Beton K-225, tebal 5 cm 11,14 m3 SNI-7394-2008. 6.7 888.560,00 9.895.004,16
3 Pasang Lantai Keramik 60/60, exs Indogress, TPZ, Kw 2 200,15 m2 SNI-7395-2008. 6.9 214.025,00 42.836.504,48
4 Pasang Lantai Keramik KM 30/30, exs Roman 8,65 m2 SNI-7395-2008. 6.36 164.380,00 1.422.347,26
5 Pasang Lantai Keramik Tempat wudhu 30/30, exs Roman 5,28 m2 SNI-7395-2008. 6.36 164.380,00 867.926,40
6 Pasang Lantai Trap Anak Tangga 40/40, unpolish 6,97 m2 SNI-7395-2008. 6.36 164.380,00 1.145.071,08
7 Pasang Step Noshing Anak Tangga Un-polish 60,00 m' Ls 142.500,00 8.550.000,00
8 Pasang Dinding Keramik tempat Wudhu+Area Mimbar sisi depan 30/50 62,40 m2 SNI-7395-2008. 6.54 184.381,00 11.505.374,40
9 Pasang Dinding Keramik kamar mandi 30x50 70,40 m2 SNI-7395-2008. 6.54 184.381,00 12.980.422,40
10 Pasang Lantai Keramik diagonal depan Gapura 40/40 23,28 m2 SNI-7395-2008. 6.36 164.380,00 3.825.944,50
11 Pasang lantai Paving Block tebal 8 cm 77,14 m2 SNI-7395-2008.6.55 84.190,00 6.494.416,60
12 Pasang dinding Batu Andesit pada Kolom 26,40 m2 Ls 250.000,00 6.600.000,00
JUMLAH A.III.a 107.373.361,36 606.764.223,33
b. PEKERJAAN FINISHING CAT LANTAI-1
1 Cat dinding interior setara Jotaplast 709,84 m2 SNI- -2002 6.13 30.155,00 21.405.089,50
2 Cat dinding eksterior setara Jotun weathershield 1229,93 m2 SNI -2002 6.13.a 37.355,00 45.943.904,41
3 Cat Plafond Gypsum setara catylac 204,80 m2 SNI -2002 6.15 21.855,00 4.475.904,00
4 Coating batu alam andesit di kolom 26,40 m2 Taksir 55.000,00 1.452.000,00
5 Mengkompon dag beton 134,56 m2 Taksir 37.000,00 4.978.720,00
JUMLAH A.III.b 78.255.617,91 685.019.841,24
c. PEKERJAAN LISTRIK/ELECTRICAL LANTAI-1
1 Pasang titik lampu, Kabel 3X2,5 mm, ETERNA 54,00 Titik ELT 6.1 235.900,00 12.738.600,00
2 Pasang Lampu Jari SL 18 watt, OSRAM+Fitting 10,00 Titik Taksir 75.000,00 750.000,00
3 Pasang Lampu Indolite TL 18 x 2 watt TKI 20,00 unit Taksir 387.000,00 7.740.000,00
4 Pasang Lampu Downlight 3" 6,00 unit Taksir 95.000,00 570.000,00
5 Pasang Lampu Tanam di Gapura Pagar 2,00 unit Taksir 350.000,00 700.000,00
6 Pasang Lampu Tempel di Kolom 16,00 unit Taksir 225.000,00 3.600.000,00
7 Pasang Box MCB 6 Ampere 1,00 unit Taksir 1.850.000,00 1.850.000,00
8 Pasang saklar Double, PANASONIC 27,00 unit Taksir 23.000,00 621.000,00
9 Pasang Stop Kontak 300 Watt, PANASONIC 14,00 unit ELT 6.2 232.600,00 3.256.400,00
10 Pasang Lampu Robyong 1,00 unit Taksir 1.250.000,001.250.000,00
JUMLAH A.III.c 33.076.000,00 718.095.841,24
d. PEKERJAAN ATAP + PLAFOND di LANTAI 1
1 Pasang rangka atap baja ringan 40,92 m2 Taksir 137.500,00 5.626.500,00
2 Pasang Penutup Atap Genteng Metal Stone Minimalis 48,00 m2 Taksir 122.000,00 5.856.000,00
3 Pasang Nok Metal Minimalis 28,00 m' Taksir 47.500,00 1.330.000,00
4 Pasang Luisplang woodplank 20,00 m' Taksir 55.000,00 1.100.000,00
5 Pasang Plafond Gypsum+GRC 204,80 m2 DIHITUNG 104.897,78 21.483.065,34
6 Pasang Lis Plafond Gypsum 366,00 m' SNI-2839.2008.6.8 25.410,00 9.300.060,00
JUMLAH A.III.d 44.695.625,34 762.791.466,58
e. PEKERJAAN SANITASI DAN PLUMBING LANTAI 1
1 Pasang Instalasi Air Bersih pipa 3/4" AW Wavin 75,00 m' RSNI T-15-2002.6.26 43.922,50 3.294.187,50
2 Pasang Kran Wastafel 3/4 4,00 set RSNI T-15-2002.6.35 131.825,00 527.300,00
3 Pasang Shower KM 4,00 set Taksir 225.000,00 900.000,00
4 Pasang Kran 3/4 8,00 set RSNI T-15-2002.6.35 131.825,00 1.054.600,00
5 Pasang Instalasi Air Kotor Pipa Pralon 3", Wavin Type D 80,00 m' RSNI-15-2002.6.31 56.512,50 4.521.000,00
6 Pasang Instalasi Air Kotor Pipa Pralon 4", Wavin Type D 66,00 m' RSNI-15-2002.6.32 64.075,00 4.228.950,00
7 Pasang Wastafel + Assesoris 4,00 set RSNI-15-2002.6.5 679.050,00 2.716.200,00
8 Pasang Closet Monoblok 2,00 set RSNI-15-2002.6.1 2.616.275,00 5.232.550,00
9 Pasang Septictank Biofil setara Biotank 1,00 set Taksir 4.500.000,00 4.500.000,00
10 Pasang Sumur Resapan 2,00 unit RSNI-15-2002.6.33 2.816.240,25 5.632.480,50
11 Pasang Bak kontrol, Pas. Bata 45x45x50 8,00 unit RSNI-15-2002.6.17 495.240,00 3.961.920,00
12 Pasang Kran Angsa Dapur 2,00 set RSNI T-15-2002.6.35 131.825,00 263.650,00
13 Pasang Tandon Air Stainless Exs "Tirta", Kap. 1000 liter 1,00 set Taksir 4.500.000,00 4.500.000,00
14 Pasang Pompa Air, Grundfos + Instalasinya 1,00 set Taksir 3.750.000,00 3.750.000,00
15 Pasang Sumur Air Bersih (Bor) 1,00 unit Taksir 4.500.000,00 4.500.000,00
16 Pasang Saluran Drainase Buis Beton U-20 80,00 m' RSNI-15-2002.6.14 88.906,00 7.112.480,00
JUMLAH A.III.e 56.695.318,00 819.486.784,58
f. PASANG KUSEN PINTU+JENDELA KACA LT 1
1 Pasang Kusen Pintu Alumunium coklat4" 57,00 m' SNI-7393-2008.6.11 111.425,00 6.351.225,00
2 Pasang Kusen Jendela Alumunium coklat 4" 84,00 m' SNI-7393-2008.6.11 111.425,00 9.359.700,00
3 Pasang Pintu Tempered (utama) 4,20 m2 SNI-PtT-30-2000.C.6.16 2.597.110,00 10.907.862,00
4 Pasang Pintu Tempered (samping) 6,30 m2 Ls 2.450.000,00 15.435.000,00
5 Pasang Pintu Frame + isi Multiplek (Gudang+Sekretariat) 6,30 m2 SNI-7393-2008.6.13.a 1.096.355,00 6.907.036,50
6 Pasang Daun Pintu KM Frame Alumunium Stripe, lebar 80 cm 5,88 m2 SNI-7393-2008.6.12 1.746.725,00 10.270.743,00
7 Pasang Daun Jendela casement isi Kaca Bening 5 mm 25,20 m2 Ls 385.000,00 9.702.000,00
8 Pasang Kaca Mati 5 mm 8,40 m2 SNI-PtT-30-2000.C.6.13 149.610,00 1.256.724,00
9 Pasang Kaca Mati 12 mm (diatas pintu utama) 1,00 m2 SNI-PtT-30-2000.C.6.13 2.597.110,00 2.597.110,00
10 Pasang Kaca Bening 8 mm Bavel 21,60 m2 Ls 295.000,00 6.372.000,00
11 Pasang Kaca Grafir diatas jendela) 2,25 m2 Ls 650.000,00 1.462.500,00
12 Pasang Glass Block 64,00 buah Ls 22.000,00 1.408.000,00
JUMLAH A.III.f 82.029.900,50 901.516.685,08
g. PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Pasang kunci tanam biasa 6,00 set SNI-PtT-30-2000.C.6.2 274.250,00 1.645.500,00
2 Pasang engsel pintu 12,00 set SNI-PtT-30-2000.C.6.5 89.250,00 1.071.000,00
3 Pasang engsel jendela 24,00 set SNI-PtT-30-2000.C.6.8 51.250,00 1.230.000,00
4 Pasang Engsel Tanam Dorma Pintu Tempered 6,00 set Taksir 1.575.000,00 9.450.000,00
5 Memasang Doorcloser 6,00 set SNI-PtT-30-2000.C.6.12 788.710,00 4.732.260,00
6 Memasang Rel Jendela Sliding dorong 12,00 set SNI-PtT-30-2000.C.6.12 396.410,00 4.756.920,00
7 Memasang Kunci Pintu Tempered 3,00 set Taksir 450.000,00 1.350.000,00
JUMLAH A.III.g 24.235.680,00 925.752.365,08
h. PEKERJAAN PELENGKAP DAN LAIN-LAIN DI LANTAI-1
1 Pekerjaan Pagar Railling Tangga+pagar Serambi 70,70 m' Taksir 450.000,00 31.815.000,00
2 Pekerjaan Atap Polycarbonat Rangka Pipa diatas Tangga 11,00 m2 Taksir 611.500,00 6.726.500,00
JUMLAH A.III.g 38.541.500,00 964.293.865,08
JUMLAH LANTAI - 1 964.293.865,08
B. LINGKUP PEKERJAAN LANTAI-2
B.I. PEKERJAAN PERSIAPAN
1 Pengukuran, Uitzet / bouwplank 163,60 m' LS 12.500,00 2.045.000,00
JUMLAH B. I 2.045.000,00 2.045.000,00
B.II. PEKERJAAN STRUKTUR
a. PEKERJAAN PASANGAN di LANTAI-2
1 Pasangan Bata 1/2 Batu, camp. 1Pc : 5 Ps 296,16 m2 SNI-6897-2008. 6.10 90.259,00 26.731.105,44
2 Plesteran Dinding camp. 1Pc : 5 Ps 640,32 m2 SNI-2837-2008. 6.5 33.785,00 21.633.211,20
3 Plesteran Beton camp. 1 Pc : 3 Ps 650,80 m2 SNI-2837-2008. 6.3 37.238,00 24.234.527,64
4 Pekerjaan Acian Dinding dan Beton 1.291,12 m2 SNI-2837-2008. 6.27 21.162,00 27.322.702,60
5 Pekerjaan Sponengan Sudut 1.968,16 m' SNI-2837-2008. 6.20 8.695,00 17.113.151,20
JUMLAH B.II.a 117.034.698,08 119.079.698,08
b. PEKERJAAN BETON di LANTAI - 2
1 Cor Beton kolom struktur K1 30x30
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 7,92 m3 SNI-7394-2008 6.8
903.815,00 7.158.214,80
b Pembesian kolom 1.142,33 kg SNI-7394-2008 6.17 10.720,50 12.246.349,97
c Begesting kolom 2 x pakai 105,60 m2 SNI-7394-2008 6.22 65.883,75 6.957.324,00
2 Cor Beton kolom struktur K2 20x20
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 2,88 m3 SNI-7394-2008 6.8
903.815,00 2.602.987,20
b Pembesian kolom 451,65 kg SNI-7394-2008 6.17 10.720,50 4.841.891,31
c Begesting kolom 2 x pakai 57,60 m2 SNI-7394-2008 6.22 65.883,75 3.794.904,00
3 Cor Beton balok struktur B1 20x35
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 8,69 m3 SNI-7394-2008.6.8
903.815,00 7.857.767,61
b Pembesian Balok 2.130,18 kg SNI-7394-2008 6.17 10.720,50 22.836.627,70
c Begesting Balok 2 x pakai 83,20 m2 SNI-7394-2008.6.23a 131.767,50 10.963.583,07
4 Cor Beton balok struktur B2 15x30
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 1,62 m3 SNI-7394-2008.6.8
903.815,00 1.464.180,30
b Pembesian Balok 356,92 kg SNI-7394-2008 6.17 10.720,50 3.826.402,76
c Begesting Balok 2 x pakai 18,36 m2 SNI-7394-2008.6.23a 131.767,50 2.419.251,30
5 Cor Beton Plat Atap/Dag Talang, tebal 10 cm
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 3,42 m3 SNI-7394-2008.6.8
903.815,00 3.091.047,30
b Pembesian Plat Atap 1.145,80 kg SNI-7394-2008 6.17 10.720,50 12.283.572,91
c Begesting Plat Atap 2 x pakai 66,00 m2 SNI-7394-2008.6.24a 161.767,50 10.676.655,00
6 Cor Beton Luisplank Lantai-2, 10x50
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 2,30 m3 SNI-7394-2008.6.8
903.815,00 2.078.774,50
b Pembesian Luisplank 399,29 kg SNI-7394-2008 6.17 10.720,50 4.280.639,05
c Begesting Luisplank 2 x pakai 23,00 m2 SNI-7394-2008.6.24a 161.767,50 3.720.652,50
7 Cor Beton Balok Latae 15x20
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 3,62 m3 SNI-7394-2008. 6.8
903.815,00 3.268.375,80
b Pembesian Balok Latae 385,57 kg SNI-7394-2008 6.17 10.720,50 4.133.492,08
c Begesting Balok 2 x pakai 72,60 m2 SNI-7394-2008.6.23a 131.767,50 9.566.320,50
8 Cor Beton Plat canopy (assesories diatas Jendela)
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 0,64 m3 SNI-7394-2008. 6.8
903.815,00 578.441,60
b Pembesian Plat canopy 40,74 kg SNI-7394-2008 6.17 10.720,50 436.735,16
c Begesting Plat canopy 2 x pakai 16,00 m2 SNI-7394-2008.6.24a 161.767,50 2.588.280,00
JUMLAH B.II.b 143.672.470,41 262.752.168,49
B.III. PEKERJAAN PASANGAN ARSITEKTURAL LANTAI-2
a. PEKERJAAN LANTAI di LANTAI-2
1 Urugan Pasir Bawah Lantai, Tebal 7 cm 8,37 m3 SNI-2835-2008. 6.11 80.200,00 671.339,52
2 Pasang Lantai Keramik 60/60, exs Indogress, TPZ, Kw 2 119,58 m2 SNI-7395-2008. 6.9 214.025,00
25.593.772,98
3 Pasang Dinding Keramik sisi depan 30/50 40,60 m2 SNI-7395-2008. 6.54 184.381,00 7.485.868,60
4 Pasang Dinding Batu Andesit pada Kolom 19,20 m2 Ls 250.000,00 4.800.000,00
JUMLAH B.III.a 38.550.981,10 301.303.149,60
b. PEKERJAAN FINISHING CAT LANTAI-2
1 Cat dinding interior setara Jotaplast 645,56 m2 SNI- -2002 6.13 30.155,00 19.466.876,88
2 Cat dinding eksterior setara Jotun weathershield 907,58 m2 SNI -2002 6.13.a 37.355,00 33.902.557,51
3 Cat Plafond Gypsum setara catylac 148,86 m2 SNI -2002 6.15 21.855,00 3.253.403,05
4 Coating batu alam andesit di kolom 19,20 m2 Taksir 55.000,00 1.056.000,00
5 Mengkompon dag beton 27,84 m2 Taksir 37.000,00 1.030.080,00
JUMLAH B.III.b 58.708.917,44 360.012.067,04
c. PEKERJAAN LISTRIK/ELECTRICAL LANTAI-2
1 Pasang titik lampu, Kabel 3X2,5 mm, ETERNA 34,00 Titik ELT 6.1 235.900,00 8.020.600,00
2 Pasang Lampu Jari SL 18 watt, OSRAM+Fitting 4,00 Titik Taksir 75.000,00 300.000,00
3 Pasang Lampu Indolite TL 18 x 2 watt TKI 8,00 unit Taksir 387.000,00 3.096.000,00
4 Pasang Lampu Downlight 3" 4,00 unit Taksir 95.000,00 380.000,00
5 Pasang Lampu Tanam di Gapura Pagar 2,00 unit Taksir 350.000,00 700.000,00
6 Pasang Lampu Tempel di Kolom 16,00 unit Taksir 225.000,00 3.600.000,00
7 Pasang Box MCB 6 Ampere 1,00 unit Taksir 1.850.000,00 1.850.000,00
8 Pasang saklar Double, PANASONIC 17,00 unit Taksir 23.000,00 391.000,00
9 Pasang Stop Kontak 300 Watt, PANASONIC 10,00 unit ELT 6.2 232.600,00 2.326.000,00
10 Pasang Lampu Robyong 1,00 unit Taksir 1.250.000,00 1.250.000,00
JUMLAH B.III.c 21.913.600,00 381.925.667,04
d. PEKERJAAN ATAP + PLAFOND di LANTAI-2
1 Pasang rangka atap baja ringan 110,00 m2 Taksir 137.500,00 15.125.000,00
2 Pasang Penutup Atap Genteng Metal Stone Minimalis 132,00 m2 Taksir 122.000,00 16.104.000,00
3 Pasang Nok Metal Minimalis 22,00 m' Taksir 47.500,00 1.045.000,00
4 Pasang Luisplang woodplank 24,00 m' Taksir 55.000,00 1.320.000,00
5 Pasang Plafond Gypsum+GRC 111,36 m2 DIHITUNG 104.897,78 11.681.416,78
6 Pasang Lis Plafond Gypsum 295,60 m' SNI-2839.2008.6.8 25.410,00 7.511.196,00
7 Pasang Kubah Stainless diameter 2 meter (Bangunan Utama) 1,00 unit Taksir 4.500.000,00 4.500.000,00
8 Pasanng Kubah Stainless diameter 1 meter (menara) 4,00 unit Taksir 750.000,00 3.000.000,00
JUMLAH B.III.d 60.286.612,78 442.212.279,82
e. PEKERJAAN SANITASI DAN PLUMBING LANTAI-2
1 Pasang Instalasi Air Hujan Pipa Pralon 3", Wavin Type D 48,00 m' RSNI-15-2002.6.31 56.512,50 2.712.600,00
2 Pasang Instalasi Air Hujan Pipa Pralon 4", Wavin Type D 48,00 m' RSNI-15-2002.6.32 64.075,00 3.075.600,00
JUMLAH B.III.e 5.788.200,00 448.000.479,82
f. PASANG KUSEN PINTU+JENDELA KACA LANTAI-2
1 Pasang Kusen Pintu Alumunium coklat 4" 18,40 m' SNI-7393-2008.6.11 111.425,00 2.050.220,00
2 Pasang Kusen Jendela Alumunium coklat 4" 126,00 m' SNI-7393-2008.6.11 111.425,00 14.039.550,00
3 Pasang Daun Pintu Frame Alumunium + isi kaca 6,30 m2 SNI-7393-2008.6.13.a 1.147.075,00 7.226.572,50
4 Pasang Daun Jendela casement isi Kaca Bening 5 mm 37,80 m2 Ls 385.000,00 14.553.000,00
5 Pasang Kaca Mati 5 mm 8,40 m2 SNI-PtT-30-2000.C.6.13 149.610,00 1.256.724,00
6 Pasang Kusen Bovenlight+kaca Mati 2,00 m2 Taksir 350.000,00 700.000,00
7 Pasang Kaca Grafir diatas jendela) 3,38 m2 Ls 650.000,00 2.193.750,00
8 Pasang Glass Block 64,00 buah Ls 22.000,00 1.408.000,00
JUMLAH B.III.f 43.427.816,50 491.428.296,32
g. PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Pasang kunci tanam biasa 2,00 set SNI-PtT-30-2000.C.6.2 274.250,00 548.500,00
2 Pasang engsel pintu 8,00 set SNI-PtT-30-2000.C.6.5 89.250,00 714.000,00
3 Pasang engsel jendela 24,00 set SNI-PtT-30-2000.C.6.8 51.250,00 1.230.000,00
4 Memasang Doorcloser 4,00 set SNI-PtT-30-2000.C.6.12 788.710,00 3.154.840,00
5 Memasang Rel Jendela Sliding dorong 12,00 set SNI-PtT-30-2000.C.6.12 396.410,00 4.756.920,00
JUMLAH B.III.g 10.404.260,00 501.832.556,32
h. PEKERJAAN PELENGKAP DAN LAIN-LAIN DI LANTAI-2
1 Pekerjaan Ornamen di sekitar Kubah utama+menara 1,00 m' Ls 10.500.000,00 10.500.000,00
2 Pekerjaan Atap Polycarbonat Rangka Pipa diatas Tangga 16,50 m2 Taksir 611.500,00 10.089.750,00
JUMLAH B.III.g 20.589.750,00 522.422.306,32
JUMLAH LANTAI-2 522.422.306,32
JUMLAH TOTAL LANTAI-1 + LANTAI-2 1.486.716.171,40
Sleman, 12 September 2013
Panitia Pembangunan Masjid Al-Amin Pedak
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : RELOKASI TEMPAT IBADAH, MESJID AL-AMIN, PEDAK
LOKASI : PEDAK, SINDUHARJO, NGAGLIK, SLEMAN, YOGYAKARTA
TAHUN ANGGARAN : 2013
NO URAIAN PEKERJAAN VOLUME SAT NO. ANALISA HARGASATUAN JUMLAH HARGA KOMULATIF SUB
(Rp.) (Rp.) (Rp.)
A. LINGKUP PEKERJAAN LANTAI-1
A.I. PEKERJAAN PERSIAPAN
1 Pengukuran, Uitzet / bouwplank 267,00 m' LS 12.500,00 3.337.500,00
2 Administrasi & dokumentasi 1,00 unit LS 750.000,00 750.000,00
3 Air kerja dan Listrik kerja 1,00 unit LS 1.500.000,00 1.500.000,00
4 Direksi keet 20,00 m2 LS 150.000,00 3.000.000,00
5 Pembersihan Lokasi 364,00 m2 LS 8.500,00 3.094.000,00
JUMLAH A. I 11.681.500,00 11.681.500,00
A.II. PEKERJAAN STRUKTUR
a. PEKERJAAN TANAH
1 Galian tanah pondasi batu+footplat kedalaman max 2,5 m 204,93 m3 SNI-2835-2008 6.3 51.940,00 10.643.804,50
2 Urugan tanah kembali bekas galian 124,15 m3 SNI-2835-2008 6.9 11.821,50 1.467.662,87
3 Urugan pasir bawah pondasi 11,75 m3 SNI-2835-2008 6.11 80.200,00 942.350,00
4 Urugan Tanah Peninggian Elevasi Bangunan+Meratakan 320,35 m3 SNI-2835-2008 6.15 90.250,00 28.911.407,00
JUMLAH A.II.a 41.965.224,37 53.646.724,37
b. PEKERJAAN PASANGAN di LANTAI 1
1 Pasang Pondasi batu kali camp 1 PC : 5 PS 50,00 m3 SNI-2836-2008. 6.3 440.725,00 22.036.250,00
2 Pasangan Bata 1/2 Batu, camp. 1Pc : 5 Ps 329,79 m2 SNI-6897-2008. 6.10 90.259,00 29.766.515,61
3 Plesteran Dinding camp. 1Pc : 5 Ps 899,58 m2 SNI-2837-2008. 6.5 33.785,00 30.392.310,30
4 Plesteran Beton camp. 1 Pc : 3 Ps 92,40 m2 SNI-2837-2008. 6.3 37.238,00 3.440.791,20
5 Pekerjaan Acian Dinding dan Beton 1.419,67 m2 SNI-2837-2008. 6.27 21.162,00 30.043.077,70
6 Pekerjaan Sponengan Sudut 1.826,16 m' SNI-2837-2008. 6.20 8.695,00 15.878.461,20
7 Pasangan Dinding rooster beton, ukuran 20x20 82,77 m2 Taksir 275.000,00 22.761.750,00
JUMLAH A.II.b 154.319.156,01 207.965.880,38
c. PEKERJAAN BETON di LANTAI - 1
1 Cor Beton Lantai Kerja
Beton mutu fc=14,5 Mpa(K175), slump (12 ± 2)cm, w/c= 0,66 2,42 m3 SNI-7394-2008. 6.5 831.510,00 2.015.580,24
2 Cor Beton Foot Plate 150x150x25 dan 100x100x25
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 10,92 m3 SNI-7394-2008. 6.8 903.815,00 9.869.659,80
b Pembesian Foot Plate 150x150 1.373,76 kg SNI-7394-2008. 6.17 10.720,50 14.727.439,23
c Begesting Foot Plate 150x150, 2 x pakai 45,00 m2 SNI-7394-2008. 6.20 27.255,00 1.226.475,00
3 Cor Beton Pedestal 30x30 dan 20x20
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 5,78 m3 SNI-7394-2008. 6.8 903.815,00 5.224.954,52
b Pembesian Pedestal 30X30 dan 20X20 682,82 kg SNI-7394-2008. 6.17 10.720,50 7.320.178,29
c Begesting Pedestal , 2 x pakai 54,00 m2 SNI-7394-2008. 6.20 27.255,00 1.471.770,00
4 Cor Beton Sloof 20x30
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 14,12 m3 SNI-7394-2008 6.5 903.815,00 12.757.348,73
b Pembesian Sloof 20/30 2.593,75 kg SNI-7394-2008 6.17 10.720,50 27.806.249,51
c Begesting Sloof 2 x pakai 141,15 m2 SNI-7394-2008 6.21 21.210,00 2.993.791,50
5 Cor Beton kolom struktur K1 30x30
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 7,43 m3 SNI-7394-2008 6.8 903.815,00 6.710.826,38
b Pembesian kolom 1.184,00 kg SNI-7394-2008 6.17 10.720,50 12.693.025,34
c Begesting kolom 2 x pakai 105,60 m2 SNI-7394-2008 6.22 43.922,50 4.638.216,00
6 Cor Beton kolom struktur K2 20x20
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 2,88 m3 SNI-7394-2008 6.8 903.815,00 2.602.987,20
b Pembesian kolom 451,65 kg SNI-7394-2008 6.17 10.720,50 4.841.891,31
c Begesting kolom 2 x pakai 57,60 m2 SNI-7394-2008 6.22 43.922,50 2.529.936,00
7 Cor Beton balok struktur B1 30x40
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 14,90 m3 SNI-7394-2008.6.8 903.815,00 13.470.458,76
b Pembesian Balok 2.130,18 kg SNI-7394-2008 6.17 10.720,50 22.836.627,70
c Begesting Balok 2 x pakai 117,30 m2 SNI-7394-2008.6.23a 87.845,00 10.304.569,88
8 Cor Beton balok struktur B2 15x30
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 1,62 m3 SNI-7394-2008.6.8 903.815,00 1.464.180,30
b Pembesian Balok 356,92 kg SNI-7394-2008 6.17 10.720,50 3.826.402,76
c Begesting Balok 2 x pakai 18,36 m2 SNI-7394-2008.6.23a 131.767,50 2.419.251,30
9 Cor Beton Plat Lantai-2/Dag, tebal 12 cm
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 23,76 m3 SNI-7394-2008.6.8 903.815,00 21.474.644,40
b Pembesian Plat Lantai 3.650,07 kg SNI-7394-2008 6.17 10.720,50 39.130.624,32
c Begesting Plat Lantai 2 x pakai 134,56 m2 SNI-7394-2008.6.24a 161.767,50 21.767.434,80
10 Cor Beton Luisplank Lantai-1, 10x50
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 2,30 m3 SNI-7394-2008.6.8 903.815,00 2.078.774,50
b Pembesian Luisplank 399,29 kg SNI-7394-2008 6.17 10.720,50 4.280.639,05
c Begesting Luisplank 2 x pakai 46,00 m2 SNI-7394-2008.6.24a 161.767,50 7.441.305,00
11 Cor Beton Tangga 2 (dua) unit di sayap utara+selatan
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 14,32 m3 SNI-7394-2008.6.8 903.815,00 12.946.133,08
b Pembesian Plat + Anak tangga 512,68 kg SNI-7394-2008 6.17 10.720,50 5.496.200,95
c Begesting Plat+Anak Tangga 2 x pakai 18,90 m2 SNI-7394-2008.6.24a 161.767,50 3.057.405,75
12 Cor Beton Balok Latae 15x20
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 3,62 m3 SNI-7394-2008. 6.8 903.815,00 3.268.375,80
b Pembesian Balok Latae 459,11 kg SNI-7394-2008 6.17 10.720,50 4.921.836,85
c Begesting Balok 2 x pakai 66,30 m2 SNI-7394-2008.6.23a 131.767,50 8.735.789,95
13 Cor Beton Kolom Praktis 15x20
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 3,83 m3 SNI-7394-2008. 6.8 903.815,00 3.457.092,38
b Pembesian Kolom Praktis 4,73 kg SNI-7394-2008 6.17 10.720,50 50.758,57
c Begesting Kolom Praktis 2 x pakai 51,00 m2 SNI-7394-2008 6.22 65.883,75 3.360.071,25
14 Cor Beton Plat canopy (assesories diatas Jendela)
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 0,64 m3 SNI-7394-2008. 6.8 903.815,00 578.441,60
b Pembesian Plat canopy 138,89 kg SNI-7394-2008 6.17 10.720,50 1.488.917,93
c Begesting Plat canopy 2 x pakai 16,00 m2 SNI-7394-2008.6.24a 161.767,50 2.588.280,00
JUMLAH A.II.c 291.424.981,58 499.390.861,96
A.III. PEKERJAAN PASANGAN ARSITEKTURAL LANTAI 1
a. PEKERJAAN LANTAI di LANTAI-1
1 Urugan Pasir Bawah Lantai, Tebal 7 cm 15,59 m3 SNI-2835-2008. 6.11 80.200,00 1.250.350,08
2 Cor Rabat Beton K-225, tebal 5 cm 11,14 m3 SNI-7394-2008. 6.7 888.560,00 9.895.004,16
3 Pasang Lantai Keramik 60/60, exs Indogress, TPZ, Kw 2 200,15 m2 SNI-7395-2008. 6.9 214.025,00 42.836.504,48
4 Pasang Lantai Keramik KM 30/30, exs Roman 8,65 m2 SNI-7395-2008. 6.36 164.380,00 1.422.347,26
5 Pasang Lantai Keramik Tempat wudhu 30/30, exs Roman 5,28 m2 SNI-7395-2008. 6.36 164.380,00 867.926,40
6 Pasang Lantai Trap Anak Tangga 40/40, unpolish 6,97 m2 SNI-7395-2008. 6.36 164.380,00 1.145.071,08
7 Pasang Step Noshing Anak Tangga Un-polish 60,00 m' Ls 142.500,00 8.550.000,00
8 Pasang Dinding Keramik tempat Wudhu+Area Mimbar sisi depan 30/50 62,40 m2 SNI-7395-2008. 6.54 184.381,00 11.505.374,40
9 Pasang Dinding Keramik kamar mandi 30x50 70,40 m2 SNI-7395-2008. 6.54 184.381,00 12.980.422,40
10 Pasang Lantai Keramik diagonal depan Gapura 40/40 23,28 m2 SNI-7395-2008. 6.36 164.380,00 3.825.944,50
11 Pasang lantai Paving Block tebal 8 cm 77,14 m2 SNI-7395-2008.6.55 84.190,00 6.494.416,60
12 Pasang dinding Batu Andesit pada Kolom 26,40 m2 Ls 250.000,00 6.600.000,00
JUMLAH A.III.a 107.373.361,36 606.764.223,33
b. PEKERJAAN FINISHING CAT LANTAI-1
1 Cat dinding interior setara Jotaplast 709,84 m2 SNI- -2002 6.13 30.155,00 21.405.089,50
2 Cat dinding eksterior setara Jotun weathershield 1229,93 m2 SNI -2002 6.13.a 37.355,00 45.943.904,41
3 Cat Plafond Gypsum setara catylac 204,80 m2 SNI -2002 6.15 21.855,00 4.475.904,00
4 Coating batu alam andesit di kolom 26,40 m2 Taksir 55.000,00 1.452.000,00
5 Mengkompon dag beton 134,56 m2 Taksir 37.000,00 4.978.720,00
JUMLAH A.III.b 78.255.617,91 685.019.841,24
c. PEKERJAAN LISTRIK/ELECTRICAL LANTAI-1
1 Pasang titik lampu, Kabel 3X2,5 mm, ETERNA 54,00 Titik ELT 6.1 235.900,00 12.738.600,00
2 Pasang Lampu Jari SL 18 watt, OSRAM+Fitting 10,00 Titik Taksir 75.000,00 750.000,00
3 Pasang Lampu Indolite TL 18 x 2 watt TKI 20,00 unit Taksir 387.000,00 7.740.000,00
4 Pasang Lampu Downlight 3" 6,00 unit Taksir 95.000,00 570.000,00
5 Pasang Lampu Tanam di Gapura Pagar 2,00 unit Taksir 350.000,00 700.000,00
6 Pasang Lampu Tempel di Kolom 16,00 unit Taksir 225.000,00 3.600.000,00
7 Pasang Box MCB 6 Ampere 1,00 unit Taksir 1.850.000,00 1.850.000,00
8 Pasang saklar Double, PANASONIC 27,00 unit Taksir 23.000,00 621.000,00
9 Pasang Stop Kontak 300 Watt, PANASONIC 14,00 unit ELT 6.2 232.600,00 3.256.400,00
10 Pasang Lampu Robyong 1,00 unit Taksir 1.250.000,001.250.000,00
JUMLAH A.III.c 33.076.000,00 718.095.841,24
d. PEKERJAAN ATAP + PLAFOND di LANTAI 1
1 Pasang rangka atap baja ringan 40,92 m2 Taksir 137.500,00 5.626.500,00
2 Pasang Penutup Atap Genteng Metal Stone Minimalis 48,00 m2 Taksir 122.000,00 5.856.000,00
3 Pasang Nok Metal Minimalis 28,00 m' Taksir 47.500,00 1.330.000,00
4 Pasang Luisplang woodplank 20,00 m' Taksir 55.000,00 1.100.000,00
5 Pasang Plafond Gypsum+GRC 204,80 m2 DIHITUNG 104.897,78 21.483.065,34
6 Pasang Lis Plafond Gypsum 366,00 m' SNI-2839.2008.6.8 25.410,00 9.300.060,00
JUMLAH A.III.d 44.695.625,34 762.791.466,58
e. PEKERJAAN SANITASI DAN PLUMBING LANTAI 1
1 Pasang Instalasi Air Bersih pipa 3/4" AW Wavin 75,00 m' RSNI T-15-2002.6.26 43.922,50 3.294.187,50
2 Pasang Kran Wastafel 3/4 4,00 set RSNI T-15-2002.6.35 131.825,00 527.300,00
3 Pasang Shower KM 4,00 set Taksir 225.000,00 900.000,00
4 Pasang Kran 3/4 8,00 set RSNI T-15-2002.6.35 131.825,00 1.054.600,00
5 Pasang Instalasi Air Kotor Pipa Pralon 3", Wavin Type D 80,00 m' RSNI-15-2002.6.31 56.512,50 4.521.000,00
6 Pasang Instalasi Air Kotor Pipa Pralon 4", Wavin Type D 66,00 m' RSNI-15-2002.6.32 64.075,00 4.228.950,00
7 Pasang Wastafel + Assesoris 4,00 set RSNI-15-2002.6.5 679.050,00 2.716.200,00
8 Pasang Closet Monoblok 2,00 set RSNI-15-2002.6.1 2.616.275,00 5.232.550,00
9 Pasang Septictank Biofil setara Biotank 1,00 set Taksir 4.500.000,00 4.500.000,00
10 Pasang Sumur Resapan 2,00 unit RSNI-15-2002.6.33 2.816.240,25 5.632.480,50
11 Pasang Bak kontrol, Pas. Bata 45x45x50 8,00 unit RSNI-15-2002.6.17 495.240,00 3.961.920,00
12 Pasang Kran Angsa Dapur 2,00 set RSNI T-15-2002.6.35 131.825,00 263.650,00
13 Pasang Tandon Air Stainless Exs "Tirta", Kap. 1000 liter 1,00 set Taksir 4.500.000,00 4.500.000,00
14 Pasang Pompa Air, Grundfos + Instalasinya 1,00 set Taksir 3.750.000,00 3.750.000,00
15 Pasang Sumur Air Bersih (Bor) 1,00 unit Taksir 4.500.000,00 4.500.000,00
16 Pasang Saluran Drainase Buis Beton U-20 80,00 m' RSNI-15-2002.6.14 88.906,00 7.112.480,00
JUMLAH A.III.e 56.695.318,00 819.486.784,58
f. PASANG KUSEN PINTU+JENDELA KACA LT 1
1 Pasang Kusen Pintu Alumunium coklat4" 57,00 m' SNI-7393-2008.6.11 111.425,00 6.351.225,00
2 Pasang Kusen Jendela Alumunium coklat 4" 84,00 m' SNI-7393-2008.6.11 111.425,00 9.359.700,00
3 Pasang Pintu Tempered (utama) 4,20 m2 SNI-PtT-30-2000.C.6.16 2.597.110,00 10.907.862,00
4 Pasang Pintu Tempered (samping) 6,30 m2 Ls 2.450.000,00 15.435.000,00
5 Pasang Pintu Frame + isi Multiplek (Gudang+Sekretariat) 6,30 m2 SNI-7393-2008.6.13.a 1.096.355,00 6.907.036,50
6 Pasang Daun Pintu KM Frame Alumunium Stripe, lebar 80 cm 5,88 m2 SNI-7393-2008.6.12 1.746.725,00 10.270.743,00
7 Pasang Daun Jendela casement isi Kaca Bening 5 mm 25,20 m2 Ls 385.000,00 9.702.000,00
8 Pasang Kaca Mati 5 mm 8,40 m2 SNI-PtT-30-2000.C.6.13 149.610,00 1.256.724,00
9 Pasang Kaca Mati 12 mm (diatas pintu utama) 1,00 m2 SNI-PtT-30-2000.C.6.13 2.597.110,00 2.597.110,00
10 Pasang Kaca Bening 8 mm Bavel 21,60 m2 Ls 295.000,00 6.372.000,00
11 Pasang Kaca Grafir diatas jendela) 2,25 m2 Ls 650.000,00 1.462.500,00
12 Pasang Glass Block 64,00 buah Ls 22.000,00 1.408.000,00
JUMLAH A.III.f 82.029.900,50 901.516.685,08
g. PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Pasang kunci tanam biasa 6,00 set SNI-PtT-30-2000.C.6.2 274.250,00 1.645.500,00
2 Pasang engsel pintu 12,00 set SNI-PtT-30-2000.C.6.5 89.250,00 1.071.000,00
3 Pasang engsel jendela 24,00 set SNI-PtT-30-2000.C.6.8 51.250,00 1.230.000,00
4 Pasang Engsel Tanam Dorma Pintu Tempered 6,00 set Taksir 1.575.000,00 9.450.000,00
5 Memasang Doorcloser 6,00 set SNI-PtT-30-2000.C.6.12 788.710,00 4.732.260,00
6 Memasang Rel Jendela Sliding dorong 12,00 set SNI-PtT-30-2000.C.6.12 396.410,00 4.756.920,00
7 Memasang Kunci Pintu Tempered 3,00 set Taksir 450.000,00 1.350.000,00
JUMLAH A.III.g 24.235.680,00 925.752.365,08
h. PEKERJAAN PELENGKAP DAN LAIN-LAIN DI LANTAI-1
1 Pekerjaan Pagar Railling Tangga+pagar Serambi 70,70 m' Taksir 450.000,00 31.815.000,00
2 Pekerjaan Atap Polycarbonat Rangka Pipa diatas Tangga 11,00 m2 Taksir 611.500,00 6.726.500,00
JUMLAH A.III.g 38.541.500,00 964.293.865,08
JUMLAH LANTAI - 1 964.293.865,08
B. LINGKUP PEKERJAAN LANTAI-2
B.I. PEKERJAAN PERSIAPAN
1 Pengukuran, Uitzet / bouwplank 163,60 m' LS 12.500,00 2.045.000,00
JUMLAH B. I 2.045.000,00 2.045.000,00
B.II. PEKERJAAN STRUKTUR
a. PEKERJAAN PASANGAN di LANTAI-2
1 Pasangan Bata 1/2 Batu, camp. 1Pc : 5 Ps 296,16 m2 SNI-6897-2008. 6.10 90.259,00 26.731.105,44
2 Plesteran Dinding camp. 1Pc : 5 Ps 640,32 m2 SNI-2837-2008. 6.5 33.785,00 21.633.211,20
3 Plesteran Beton camp. 1 Pc : 3 Ps 650,80 m2 SNI-2837-2008. 6.3 37.238,00 24.234.527,64
4 Pekerjaan Acian Dinding dan Beton 1.291,12 m2 SNI-2837-2008. 6.27 21.162,00 27.322.702,60
5 Pekerjaan Sponengan Sudut 1.968,16 m' SNI-2837-2008. 6.20 8.695,00 17.113.151,20
JUMLAH B.II.a 117.034.698,08 119.079.698,08
b. PEKERJAAN BETON di LANTAI - 2
1 Cor Beton kolom struktur K1 30x30
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 7,92 m3 SNI-7394-2008 6.8
903.815,00 7.158.214,80
b Pembesian kolom 1.142,33 kg SNI-7394-2008 6.17 10.720,50 12.246.349,97
c Begesting kolom 2 x pakai 105,60 m2 SNI-7394-2008 6.22 65.883,75 6.957.324,00
2 Cor Beton kolom struktur K2 20x20
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 2,88 m3 SNI-7394-2008 6.8
903.815,00 2.602.987,20
b Pembesian kolom 451,65 kg SNI-7394-2008 6.17 10.720,50 4.841.891,31
c Begesting kolom 2 x pakai 57,60 m2 SNI-7394-2008 6.22 65.883,75 3.794.904,00
3 Cor Beton balok struktur B1 20x35
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 8,69 m3 SNI-7394-2008.6.8
903.815,00 7.857.767,61
b Pembesian Balok 2.130,18 kg SNI-7394-2008 6.17 10.720,50 22.836.627,70
c Begesting Balok 2 x pakai 83,20 m2 SNI-7394-2008.6.23a 131.767,50 10.963.583,07
4 Cor Beton balok struktur B2 15x30
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 1,62 m3 SNI-7394-2008.6.8
903.815,00 1.464.180,30
b Pembesian Balok 356,92 kg SNI-7394-2008 6.17 10.720,50 3.826.402,76
c Begesting Balok 2 x pakai 18,36 m2 SNI-7394-2008.6.23a 131.767,50 2.419.251,30
5 Cor Beton Plat Atap/Dag Talang, tebal 10 cm
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 3,42 m3 SNI-7394-2008.6.8
903.815,00 3.091.047,30
b Pembesian Plat Atap 1.145,80 kg SNI-7394-2008 6.17 10.720,50 12.283.572,91
c Begesting Plat Atap 2 x pakai 66,00 m2 SNI-7394-2008.6.24a 161.767,50 10.676.655,00
6 Cor Beton Luisplank Lantai-2, 10x50
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 2,30 m3 SNI-7394-2008.6.8
903.815,00 2.078.774,50
b Pembesian Luisplank 399,29 kg SNI-7394-2008 6.17 10.720,50 4.280.639,05
c Begesting Luisplank 2 x pakai 23,00 m2 SNI-7394-2008.6.24a 161.767,50 3.720.652,50
7 Cor Beton Balok Latae 15x20
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 3,62 m3 SNI-7394-2008. 6.8
903.815,00 3.268.375,80
b Pembesian Balok Latae 385,57 kg SNI-7394-2008 6.17 10.720,50 4.133.492,08
c Begesting Balok 2 x pakai 72,60 m2 SNI-7394-2008.6.23a 131.767,50 9.566.320,50
8 Cor Beton Plat canopy (assesories diatas Jendela)
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 0,64 m3 SNI-7394-2008. 6.8
903.815,00 578.441,60
b Pembesian Plat canopy 40,74 kg SNI-7394-2008 6.17 10.720,50 436.735,16
c Begesting Plat canopy 2 x pakai 16,00 m2 SNI-7394-2008.6.24a 161.767,50 2.588.280,00
JUMLAH B.II.b 143.672.470,41 262.752.168,49
B.III. PEKERJAAN PASANGAN ARSITEKTURAL LANTAI-2
a. PEKERJAAN LANTAI di LANTAI-2
1 Urugan Pasir Bawah Lantai, Tebal 7 cm 8,37 m3 SNI-2835-2008. 6.11 80.200,00 671.339,52
2 Pasang Lantai Keramik 60/60, exs Indogress, TPZ, Kw 2 119,58 m2 SNI-7395-2008. 6.9 214.025,00
25.593.772,98
3 Pasang Dinding Keramik sisi depan 30/50 40,60 m2 SNI-7395-2008. 6.54 184.381,00 7.485.868,60
4 Pasang Dinding Batu Andesit pada Kolom 19,20 m2 Ls 250.000,00 4.800.000,00
JUMLAH B.III.a 38.550.981,10 301.303.149,60
b. PEKERJAAN FINISHING CAT LANTAI-2
1 Cat dinding interior setara Jotaplast 645,56 m2 SNI- -2002 6.13 30.155,00 19.466.876,88
2 Cat dinding eksterior setara Jotun weathershield 907,58 m2 SNI -2002 6.13.a 37.355,00 33.902.557,51
3 Cat Plafond Gypsum setara catylac 148,86 m2 SNI -2002 6.15 21.855,00 3.253.403,05
4 Coating batu alam andesit di kolom 19,20 m2 Taksir 55.000,00 1.056.000,00
5 Mengkompon dag beton 27,84 m2 Taksir 37.000,00 1.030.080,00
JUMLAH B.III.b 58.708.917,44 360.012.067,04
c. PEKERJAAN LISTRIK/ELECTRICAL LANTAI-2
1 Pasang titik lampu, Kabel 3X2,5 mm, ETERNA 34,00 Titik ELT 6.1 235.900,00 8.020.600,00
2 Pasang Lampu Jari SL 18 watt, OSRAM+Fitting 4,00 Titik Taksir 75.000,00 300.000,00
3 Pasang Lampu Indolite TL 18 x 2 watt TKI 8,00 unit Taksir 387.000,00 3.096.000,00
4 Pasang Lampu Downlight 3" 4,00 unit Taksir 95.000,00 380.000,00
5 Pasang Lampu Tanam di Gapura Pagar 2,00 unit Taksir 350.000,00 700.000,00
6 Pasang Lampu Tempel di Kolom 16,00 unit Taksir 225.000,00 3.600.000,00
7 Pasang Box MCB 6 Ampere 1,00 unit Taksir 1.850.000,00 1.850.000,00
8 Pasang saklar Double, PANASONIC 17,00 unit Taksir 23.000,00 391.000,00
9 Pasang Stop Kontak 300 Watt, PANASONIC 10,00 unit ELT 6.2 232.600,00 2.326.000,00
10 Pasang Lampu Robyong 1,00 unit Taksir 1.250.000,00 1.250.000,00
JUMLAH B.III.c 21.913.600,00 381.925.667,04
d. PEKERJAAN ATAP + PLAFOND di LANTAI-2
1 Pasang rangka atap baja ringan 110,00 m2 Taksir 137.500,00 15.125.000,00
2 Pasang Penutup Atap Genteng Metal Stone Minimalis 132,00 m2 Taksir 122.000,00 16.104.000,00
3 Pasang Nok Metal Minimalis 22,00 m' Taksir 47.500,00 1.045.000,00
4 Pasang Luisplang woodplank 24,00 m' Taksir 55.000,00 1.320.000,00
5 Pasang Plafond Gypsum+GRC 111,36 m2 DIHITUNG 104.897,78 11.681.416,78
6 Pasang Lis Plafond Gypsum 295,60 m' SNI-2839.2008.6.8 25.410,00 7.511.196,00
7 Pasang Kubah Stainless diameter 2 meter (Bangunan Utama) 1,00 unit Taksir 4.500.000,00 4.500.000,00
8 Pasanng Kubah Stainless diameter 1 meter (menara) 4,00 unit Taksir 750.000,00 3.000.000,00
JUMLAH B.III.d 60.286.612,78 442.212.279,82
e. PEKERJAAN SANITASI DAN PLUMBING LANTAI-2
1 Pasang Instalasi Air Hujan Pipa Pralon 3", Wavin Type D 48,00 m' RSNI-15-2002.6.31 56.512,50 2.712.600,00
2 Pasang Instalasi Air Hujan Pipa Pralon 4", Wavin Type D 48,00 m' RSNI-15-2002.6.32 64.075,00 3.075.600,00
JUMLAH B.III.e 5.788.200,00 448.000.479,82
f. PASANG KUSEN PINTU+JENDELA KACA LANTAI-2
1 Pasang Kusen Pintu Alumunium coklat 4" 18,40 m' SNI-7393-2008.6.11 111.425,00 2.050.220,00
2 Pasang Kusen Jendela Alumunium coklat 4" 126,00 m' SNI-7393-2008.6.11 111.425,00 14.039.550,00
3 Pasang Daun Pintu Frame Alumunium + isi kaca 6,30 m2 SNI-7393-2008.6.13.a 1.147.075,00 7.226.572,50
4 Pasang Daun Jendela casement isi Kaca Bening 5 mm 37,80 m2 Ls 385.000,00 14.553.000,00
5 Pasang Kaca Mati 5 mm 8,40 m2 SNI-PtT-30-2000.C.6.13 149.610,00 1.256.724,00
6 Pasang Kusen Bovenlight+kaca Mati 2,00 m2 Taksir 350.000,00 700.000,00
7 Pasang Kaca Grafir diatas jendela) 3,38 m2 Ls 650.000,00 2.193.750,00
8 Pasang Glass Block 64,00 buah Ls 22.000,00 1.408.000,00
JUMLAH B.III.f 43.427.816,50 491.428.296,32
g. PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Pasang kunci tanam biasa 2,00 set SNI-PtT-30-2000.C.6.2 274.250,00 548.500,00
2 Pasang engsel pintu 8,00 set SNI-PtT-30-2000.C.6.5 89.250,00 714.000,00
3 Pasang engsel jendela 24,00 set SNI-PtT-30-2000.C.6.8 51.250,00 1.230.000,00
4 Memasang Doorcloser 4,00 set SNI-PtT-30-2000.C.6.12 788.710,00 3.154.840,00
5 Memasang Rel Jendela Sliding dorong 12,00 set SNI-PtT-30-2000.C.6.12 396.410,00 4.756.920,00
JUMLAH B.III.g 10.404.260,00 501.832.556,32
h. PEKERJAAN PELENGKAP DAN LAIN-LAIN DI LANTAI-2
1 Pekerjaan Ornamen di sekitar Kubah utama+menara 1,00 m' Ls 10.500.000,00 10.500.000,00
2 Pekerjaan Atap Polycarbonat Rangka Pipa diatas Tangga 16,50 m2 Taksir 611.500,00 10.089.750,00
JUMLAH B.III.g 20.589.750,00 522.422.306,32
JUMLAH LANTAI-2 522.422.306,32
JUMLAH TOTAL LANTAI-1 + LANTAI-2 1.486.716.171,40
Sleman, 12 September 2013
Panitia Pembangunan Masjid Al-Amin Pedak
Minggu, 03 November 2013
PROPOSAL RELOKASI PEMBANGUNAN MASJID AL AMIN
PANITIA RELOKASI PEMBANGUNAN MASJID AL-AMIN
Sekretariat: Pedukuhan Pedak, Sinduharjon Ngaglik, Sleman, DI Yogyakarta 55581
Contact Person : Slamet Ludiyono, S.Pd HP.081802651595,
Yadi Yunus, M.Eng HP.08156886043
Sleman, 12 September 2013
No : 01/PP Al-Amin/IX/2013
Lampiran : 1 berkas
Hal : Proposal Relokasi pembangunan Masjid Al Amin
Kepada :
Yth. Bapak, Ibu, Saudara...
Assalamu’alaikum Warahmatullahi Wabarakatuh,
Teriring salam ta’dzim kami sampaikan, semoga Bapak, Ibu dan saudara selalu dalam keberkahan dan lindungan Allah SWT. Shalawat dan salam semoga tercurah kepada Nabi Muhammad SAW, amin ya robbal ‘alamin.
“Perumpamaan orang-orang yang menafkahkan hartanya di jalan Allah adalah serupa dangan sebutir benih yang menumbuhkan tujuh butir, pada tiap-tiap butir tumbuh 100 biji,. Allah melipatgandakan bagi siapa yang dikehendaki. Dan Allah Maha Luas lagi Maha Mengetahui” (QS. Al-Baqarah 261)
Sehubungan dengan firman Allah tersebut di atas, kami mengajak Bapak, Ibu dan Saudara untuk berpartisipasi aktif dalam pelaksanaan relokasi Masjid Al-Amin di Pedukuhan Pedak dengan menyisihkan sebagian rezekinya baik dalam bentuk zakat, infaq atau shodaqoh sebagai investasi akhirat.
Penyaluran bantuan dapat dilakukan melalui transfer ke Rekening Bank Syariah Mandiri atas nama MASJID AL-AMIN, No. Rekening: 0940045015 dan bisa juga ke Bank BPD DIY Capem Pakem atas nama Takmir Masjid Al Amin No.Rek. : 041.221.010021 Atau langsung ke Sekretariat Relokasi Pembangunan Masjid di Pedukuhan Pedak, Desa Sinduharjo, Kecamatan Ngaglik, Kabupaten Sleman, DI Yogyakarta. Insya Allah dengan doa restu dan bantuan Bapak, Ibu, Saudara, kami yakin rencana relokasi Masjid akan segera terwujud.
Partisipasi dan bantuan Bapak, Ibu dan saudara semoga menjadi amal shalih di sisi Allah SWT, dan mendapat balasan yang berlipat ganda, dimudahkan segala urusannya serta diberkahi, amin ya robbal ‘alamin. Billahittaufiq wal hidayah, assalamu’alaikum warahmatullahi wabarokatuh.
Dukuh Pedak
Ginanto
Takmir Masjid
Slamet Ludiyono, S.Pd. Ketua
Ketua Panitia
Yadi Yunus, M.Eng
Mengetahui:
Kepala Desa Sinduharjo
M. Sidik Wahyudi
I. PENDAHULUAN
Pesatnya perubahan di era globalisasi, canggihnya teknologi komunikasi juga pertumbuhan yang pesat berdampak positif dan negatif, berpengaruh pada perubahan nilai dan tatanan kehidupan sosial kemasyarakatan, terutama di bidang mental spiritual, dan akhlak. Untuk mengantisipasi dan sebagai jawaban terhadap tantangan itu dibutuhkan sarana penunjang peribadatan. Dalam hal ini sebuah Masjid yang representatif sebagai benteng dan pusat pembinaan mental spiritual dan akhlak seluruh warga muslim Pedukuhan Pedak dan masyarakat sekitar serta umat muslim pada umumnya
II. LATAR BELAKANG
Di Pedukuhan Pedak, Desa Sinduharjo, Kecamatan Ngaglik, Kabupaten Sleman, DI Yogyakarta memiliki masjid yang dibuat sejak tahun 1984 di atas tanah kas desa yang tidak memiliki legalitas formal dan pengurusannya terkendala peraturan yang berlaku. Sementara itu dengan berjalannya waktu dan semakin meningkatnya kesadaran warga muslim di Pedukuhan Pedak dan masyarakat disekitarnya, maka keberadaan dan kondisi masjid semakin kurang memadai. Jika shalat Jum’ah, Ramadhan, Idul Fitri, dan Idul Adha tidak bisa menampung jamaah. Sejak masjid didirikan sampai sekarang belum mengalami perubahan yang signifikan, namun apabila dilakukan perbaikan dan perluasan terkendala oleh status tanah yang menurut sejarah di Desa Sinduharjo belum ada yang berhasil. Mengingat pertumbuhan kesadaran warga yang begitu cepat dan melihat kondisi yang sedemikian rupa serta didorong rasa tanggung jawab terhadap syi’ar Islam dan Ummat, timbul niat, tekad, dan keinginan yang kuat untuk membangun Masjid yang lebih representatif, sebagaimana yang didambakan dan dibutuhkan oleh umat Islam di wilayah Pedukuhan Pedak. Alhamdulillah keluarga Ibu Sumarsih didukung oleh semua anak dan cucu mewakafkan tanahnya seluas ± 500 m² untuk merelokasi masjid yang menjadi dambaan umat islam di Pedukuhan Pedak.
.
III. TUJUAN
Membangun masjid yang representative di Pedukuhan Pedak dalam rangka mewujudkan:
a. Pengamalan Al-Qur’an dan Assunah.
b. Kenyamanan beribadah untuk menumbuhkan cinta kepada Allah dan Rasul-Nya.
c. Mendorong umat untuk malaksanakan amar ma’ruf & nahi munkar
d. Memperkuat Ukhuwah Islamiyah.
e. Pendidikan da’wah dan kegiatan lain yang bernafaskan Islam.
f. Pengembangan akhlak, mental & spiritual.
IV. KEGIATAN
Nama kegiatan : “ RELOKASI PEMBANGUNAN MASJID AL - AMIN“
Bentuk Kegiatan :
a. Persiapan administrasi dan pengurusan surat-surat Masjid.
b. Kerja bakti warga secara berkala pada lahan sekitar Masjid.
c. Penggalangan dana.
d. Pembangunan fisik Masjid.
V. DESAIN DAN LOKASI MASJID
Masjid akan didirikan diatas tanah seluas ± 500 m2, yang merupakan tanah wakaf. Lokasi Masjid berada di Pedukuhan Pedak, Desa Sinduharjo, Kecamatan Ngaglik, Kabupaten Sleman, Daerah Istimewa Yogyakarta
Ukuran Masjid AL-AMIN adalah sebagai berikut:
Panjang x Lebar : 18 x 11,6 m2 = 208,8 m2
Luas Bangunan : Lantai 1 : 208,8 m2
Lantai 2 : 185,6 m2
Total 394,4 m2
Tinggi atap : 12 m
Penutup atap : Baja ringan dan dak
Kapasitas : Lantai 1 : 212 Jamaah
Lantai 2 : 285
Total : 497 jamah
Fasilitas dan sarana penunjang : kantor sekretariat, dapur, dan gudang
Rencana Anggaran Biaya (RAB) menghabiskan dana sekitar Rp1.486.716.171,40 ( Satu miliar empatratus delapanpuluh enam juta tujuhratus enambelas ribu seratus tujuhpuluh satu rupiah empatpuluh sen). RAB secara rinci dan desain terlampir.
VI. PANITIA RELOKASI PEMBANGUNAN MASJID MASJID
Adapun susunan Panitia Relokasi Masjid adalah sebagai berikut :
Pelindung : M. Sidik Wahyudi (Kepala Desa Sinduharjo)
Penasihat :
1. Ginanto (Dukuh Pedak)
1. Ginanto (Dukuh Pedak)
2. Wiyono
Penanggung Jawab : Slamet Ludiyono, S.Pd. (Ketua Takmir Masjid)
Ketua I : Yadi Yunus, M.Eng
Ketua II : Wahono
Sekretaris:
1. Parwoto, SH.
2. Uling Sumbogo, S.IP
1. Parwoto, SH.
2. Uling Sumbogo, S.IP
Bendahara :
1. Drs. Astadi
2. Samidi
1. Drs. Astadi
2. Samidi
Seksi penggalang dana
1. H.Sukarjo
2. H. Untoro
3. H. Sugiran
4. Narto
5. Drs. Nuryadi
6. Basuki
7. H. Nurul
8. Gandi
9. Suyadi,B.A
10. Hidayatun
11. Darni
12. Drs.Suyudi
13. Agus Sudiraharjo
Seksi perlengkapan :
1. Sudiman
2. Sumarjan
1. Sudiman
2. Sumarjan
3. Joko
4. Adji Satriawan
Seksi konsumsi Ibu – ibu di RT 01,RT 02,RT 03, RT 04
Seksi publikasi
1. Arival
1. Arival
2. Aryoko Wibowo
VII. . PENDANAAN
Sumber Dana:
1. Umat Islam warga Pedukuhan Pedak
2. Donatur perorangan.
3. Donatur lembaga
Penggalangan Dana:
1. Berusaha mencari dan menerima bantuan dari sumber-sumber yang halal
2. Mengumpulkan ZIS dari masyarakat dengan sukarela.
VIII PENUTUP
Proposal ini dibuat dengan harapan semoga akan mendapat doa restu, respon positif, dan bantuan Bapak, Ibu, dan Saudara sehingga dapat terlaksana pembangunan Masjid di Pedukuhan Pedak. Bantuan, sumbangan atau amal jariyah, zakat, infaq dan shadaqoh Bapak, Ibu, Saudara sekalian dapat disalurkan melalui ;
1. Sekretariat Panitia Relokasi Masjid, dengan alamat:
Pedukuhan Pedak, Desa Sinduharjo, Kecamatan Ngaglik, Kabupaten Sleman, Daerah Istimewa Yogyakarta. No HP.081802651595, 08156886043.
2. Bank Syariah Mandiri atas nama MASJID AL-AMIN, No. Rekening: 0940045015 dan bisa juga
ke Bank BPD DIY Capem Pakem atas nama Takmir Masjid Al Amin No.Rek. : 041.221.010021
ke Bank BPD DIY Capem Pakem atas nama Takmir Masjid Al Amin No.Rek. : 041.221.010021
Contak Person : Slamet Ludiyono, S.Pd HP.081802651595, Yadi Yunus, M.Eng HP. 08156886043.
Kami berdo’a kepada Allah, semoga apa yang Bapak, Ibu, Saudara berikan untuk relokasi Masjid Al-Amin mendapat ridha dan balasan yang berlipat ganda oleh Allah SWT, Amin ya robbal ‘alamin.
Sleman, 25 Oktober 2013
Langganan: