ESTIMASI :
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : RELOKASI TEMPAT IBADAH, MESJID AL-AMIN, PEDAK
LOKASI : PEDAK, SINDUHARJO, NGAGLIK, SLEMAN, YOGYAKARTA
TAHUN ANGGARAN : 2013

NO URAIAN PEKERJAAN VOLUME SAT NO. ANALISA HARGASATUAN JUMLAH HARGA KOMULATIF SUB
(Rp.) (Rp.)                                                                                                                                        (Rp.)
A. LINGKUP PEKERJAAN LANTAI-1
A.I. PEKERJAAN PERSIAPAN
1 Pengukuran, Uitzet / bouwplank 267,00 m' LS                                       12.500,00              3.337.500,00
2 Administrasi & dokumentasi 1,00 unit LS                                             750.000,00                 750.000,00
3 Air kerja dan Listrik kerja 1,00 unit LS                                             1.500.000,00              1.500.000,00
4 Direksi keet 20,00 m2 LS                                                                    150.000,00             3.000.000,00
5 Pembersihan Lokasi 364,00 m2 LS                                                          8.500,00             3.094.000,00
                                                                                   JUMLAH A. I 11.681.500,00          11.681.500,00
A.II. PEKERJAAN STRUKTUR
a. PEKERJAAN TANAH
1 Galian tanah pondasi batu+footplat kedalaman max 2,5 m 204,93 m3  SNI-2835-2008 6.3 51.940,00        10.643.804,50
2 Urugan tanah kembali bekas galian 124,15 m3 SNI-2835-2008 6.9 11.821,50 1.467.662,87
3 Urugan pasir bawah pondasi 11,75 m3 SNI-2835-2008 6.11 80.200,00 942.350,00
4 Urugan Tanah Peninggian Elevasi Bangunan+Meratakan 320,35 m3 SNI-2835-2008 6.15 90.250,00 28.911.407,00
                                                                                  JUMLAH A.II.a 41.965.224,37        53.646.724,37
b. PEKERJAAN PASANGAN di LANTAI 1
1 Pasang Pondasi batu kali camp 1 PC : 5 PS 50,00 m3 SNI-2836-2008. 6.3 440.725,00 22.036.250,00
2 Pasangan Bata 1/2 Batu, camp. 1Pc : 5 Ps 329,79 m2 SNI-6897-2008. 6.10 90.259,00 29.766.515,61
3 Plesteran Dinding camp. 1Pc : 5 Ps 899,58 m2 SNI-2837-2008. 6.5 33.785,00 30.392.310,30
4 Plesteran Beton camp. 1 Pc : 3 Ps 92,40 m2 SNI-2837-2008. 6.3 37.238,00 3.440.791,20
5 Pekerjaan Acian Dinding dan Beton 1.419,67 m2 SNI-2837-2008. 6.27 21.162,00 30.043.077,70
6 Pekerjaan Sponengan Sudut 1.826,16 m' SNI-2837-2008. 6.20 8.695,00 15.878.461,20
7 Pasangan Dinding rooster beton, ukuran 20x20 82,77 m2 Taksir 275.000,00 22.761.750,00
                                                                            JUMLAH A.II.b 154.319.156,01          207.965.880,38

c. PEKERJAAN BETON di LANTAI - 1
1 Cor Beton Lantai Kerja
Beton mutu fc=14,5 Mpa(K175), slump (12 ± 2)cm, w/c= 0,66 2,42 m3 SNI-7394-2008. 6.5 831.510,00 2.015.580,24
2 Cor Beton Foot Plate 150x150x25 dan 100x100x25
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 10,92 m3 SNI-7394-2008. 6.8 903.815,00 9.869.659,80
b Pembesian Foot Plate 150x150 1.373,76 kg SNI-7394-2008. 6.17 10.720,50 14.727.439,23
c Begesting Foot Plate 150x150, 2 x pakai 45,00 m2 SNI-7394-2008. 6.20 27.255,00 1.226.475,00
3 Cor Beton Pedestal 30x30 dan 20x20
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 5,78 m3 SNI-7394-2008. 6.8 903.815,00 5.224.954,52
b Pembesian Pedestal 30X30 dan 20X20 682,82 kg SNI-7394-2008. 6.17 10.720,50 7.320.178,29
c Begesting Pedestal , 2 x pakai 54,00 m2 SNI-7394-2008. 6.20 27.255,00 1.471.770,00
4 Cor Beton Sloof 20x30
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 14,12 m3 SNI-7394-2008 6.5 903.815,00 12.757.348,73
b Pembesian Sloof 20/30 2.593,75 kg SNI-7394-2008 6.17 10.720,50 27.806.249,51
c Begesting Sloof 2 x pakai 141,15 m2 SNI-7394-2008 6.21 21.210,00 2.993.791,50
5 Cor Beton kolom struktur K1 30x30
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 7,43 m3 SNI-7394-2008 6.8 903.815,00 6.710.826,38
b Pembesian kolom 1.184,00 kg SNI-7394-2008 6.17 10.720,50 12.693.025,34
c Begesting kolom 2 x pakai 105,60 m2 SNI-7394-2008 6.22 43.922,50 4.638.216,00
6 Cor Beton kolom struktur K2 20x20
 a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 2,88 m3 SNI-7394-2008 6.8 903.815,00 2.602.987,20
b Pembesian kolom 451,65 kg SNI-7394-2008 6.17 10.720,50 4.841.891,31
c Begesting kolom 2 x pakai 57,60 m2 SNI-7394-2008 6.22 43.922,50 2.529.936,00
7 Cor Beton balok struktur B1 30x40
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 14,90 m3 SNI-7394-2008.6.8 903.815,00 13.470.458,76
b Pembesian Balok 2.130,18 kg SNI-7394-2008 6.17 10.720,50 22.836.627,70
c Begesting Balok 2 x pakai 117,30 m2 SNI-7394-2008.6.23a 87.845,00 10.304.569,88
8 Cor Beton balok struktur B2 15x30
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 1,62 m3 SNI-7394-2008.6.8 903.815,00 1.464.180,30
b Pembesian Balok 356,92 kg SNI-7394-2008 6.17 10.720,50 3.826.402,76
c Begesting Balok 2 x pakai 18,36 m2 SNI-7394-2008.6.23a 131.767,50 2.419.251,30
9 Cor Beton Plat Lantai-2/Dag, tebal 12 cm
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 23,76 m3 SNI-7394-2008.6.8 903.815,00 21.474.644,40
b Pembesian Plat Lantai 3.650,07 kg SNI-7394-2008 6.17 10.720,50 39.130.624,32
c Begesting Plat Lantai 2 x pakai 134,56 m2 SNI-7394-2008.6.24a 161.767,50 21.767.434,80
10 Cor Beton Luisplank Lantai-1, 10x50
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 2,30 m3 SNI-7394-2008.6.8 903.815,00 2.078.774,50
b Pembesian Luisplank 399,29 kg SNI-7394-2008 6.17 10.720,50 4.280.639,05
c Begesting Luisplank 2 x pakai 46,00 m2 SNI-7394-2008.6.24a 161.767,50 7.441.305,00
11 Cor Beton Tangga 2 (dua) unit di sayap utara+selatan
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 14,32 m3 SNI-7394-2008.6.8 903.815,00 12.946.133,08
b Pembesian Plat + Anak tangga 512,68 kg SNI-7394-2008 6.17 10.720,50 5.496.200,95
c Begesting Plat+Anak Tangga 2 x pakai 18,90 m2 SNI-7394-2008.6.24a 161.767,50 3.057.405,75
12 Cor Beton Balok Latae 15x20
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 3,62 m3 SNI-7394-2008. 6.8 903.815,00 3.268.375,80
b Pembesian Balok Latae 459,11 kg SNI-7394-2008 6.17 10.720,50 4.921.836,85
c Begesting Balok 2 x pakai 66,30 m2 SNI-7394-2008.6.23a 131.767,50 8.735.789,95
13 Cor Beton Kolom Praktis 15x20
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 3,83 m3 SNI-7394-2008. 6.8 903.815,00 3.457.092,38
b Pembesian Kolom Praktis 4,73 kg SNI-7394-2008 6.17 10.720,50 50.758,57
c Begesting Kolom Praktis 2 x pakai 51,00 m2 SNI-7394-2008 6.22 65.883,75 3.360.071,25
14 Cor Beton Plat canopy (assesories diatas Jendela)
a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 0,64 m3 SNI-7394-2008. 6.8 903.815,00 578.441,60
b Pembesian Plat canopy 138,89 kg SNI-7394-2008 6.17 10.720,50 1.488.917,93
c Begesting Plat canopy 2 x pakai 16,00 m2 SNI-7394-2008.6.24a 161.767,50 2.588.280,00

                                                                            JUMLAH A.II.c 291.424.981,58       499.390.861,96
A.III. PEKERJAAN PASANGAN ARSITEKTURAL LANTAI 1
a. PEKERJAAN LANTAI di LANTAI-1
1 Urugan Pasir Bawah Lantai, Tebal 7 cm 15,59 m3 SNI-2835-2008. 6.11 80.200,00 1.250.350,08
2 Cor Rabat Beton K-225, tebal 5 cm 11,14 m3 SNI-7394-2008. 6.7 888.560,00 9.895.004,16
3 Pasang Lantai Keramik 60/60, exs Indogress, TPZ, Kw 2 200,15 m2 SNI-7395-2008. 6.9 214.025,00 42.836.504,48
4 Pasang Lantai Keramik KM 30/30, exs Roman 8,65 m2 SNI-7395-2008. 6.36 164.380,00 1.422.347,26
5 Pasang Lantai Keramik Tempat wudhu 30/30, exs Roman 5,28 m2 SNI-7395-2008. 6.36 164.380,00 867.926,40
6 Pasang Lantai Trap Anak Tangga 40/40, unpolish 6,97 m2 SNI-7395-2008. 6.36 164.380,00 1.145.071,08
7 Pasang Step Noshing Anak Tangga Un-polish 60,00 m' Ls 142.500,00 8.550.000,00
8 Pasang Dinding Keramik tempat Wudhu+Area Mimbar sisi depan 30/50 62,40 m2 SNI-7395-2008. 6.54 184.381,00 11.505.374,40
9 Pasang Dinding Keramik kamar mandi 30x50 70,40 m2 SNI-7395-2008. 6.54 184.381,00 12.980.422,40
10 Pasang Lantai Keramik diagonal depan Gapura 40/40 23,28 m2 SNI-7395-2008. 6.36 164.380,00 3.825.944,50
11 Pasang lantai Paving Block tebal 8 cm 77,14 m2 SNI-7395-2008.6.55 84.190,00 6.494.416,60
12 Pasang dinding Batu Andesit pada Kolom 26,40 m2 Ls 250.000,00 6.600.000,00
                                                                        JUMLAH A.III.a 107.373.361,36            606.764.223,33
b. PEKERJAAN FINISHING CAT LANTAI-1
1 Cat dinding interior setara Jotaplast 709,84 m2 SNI- -2002 6.13 30.155,00 21.405.089,50
2 Cat dinding eksterior setara Jotun weathershield 1229,93 m2 SNI -2002 6.13.a 37.355,00 45.943.904,41
3 Cat Plafond Gypsum setara catylac 204,80 m2 SNI -2002 6.15 21.855,00 4.475.904,00
4 Coating batu alam andesit di kolom 26,40 m2 Taksir 55.000,00 1.452.000,00
5 Mengkompon dag beton 134,56 m2 Taksir 37.000,00 4.978.720,00
                                                                            JUMLAH A.III.b 78.255.617,91           685.019.841,24
c. PEKERJAAN LISTRIK/ELECTRICAL LANTAI-1
1 Pasang titik lampu, Kabel 3X2,5 mm, ETERNA 54,00 Titik ELT 6.1 235.900,00 12.738.600,00
2 Pasang Lampu Jari SL 18 watt, OSRAM+Fitting 10,00 Titik Taksir 75.000,00 750.000,00
3 Pasang Lampu Indolite TL 18 x 2 watt TKI 20,00 unit Taksir 387.000,00 7.740.000,00
4 Pasang Lampu Downlight 3" 6,00 unit Taksir 95.000,00 570.000,00
5 Pasang Lampu Tanam di Gapura Pagar 2,00 unit Taksir 350.000,00 700.000,00
6 Pasang Lampu Tempel di Kolom 16,00 unit Taksir 225.000,00 3.600.000,00
7 Pasang Box MCB 6 Ampere 1,00 unit Taksir 1.850.000,00 1.850.000,00
8 Pasang saklar Double, PANASONIC 27,00 unit Taksir 23.000,00 621.000,00
9 Pasang Stop Kontak 300 Watt, PANASONIC 14,00 unit ELT 6.2 232.600,00 3.256.400,00
10 Pasang Lampu Robyong 1,00 unit Taksir 1.250.000,001.250.000,00
                                                                     JUMLAH A.III.c 33.076.000,00                  718.095.841,24
d. PEKERJAAN ATAP + PLAFOND di LANTAI 1
1 Pasang rangka atap baja ringan 40,92 m2 Taksir 137.500,00 5.626.500,00
2 Pasang Penutup Atap Genteng Metal Stone Minimalis 48,00 m2 Taksir 122.000,00 5.856.000,00
3 Pasang Nok Metal Minimalis 28,00 m' Taksir 47.500,00 1.330.000,00
4 Pasang Luisplang woodplank 20,00 m' Taksir 55.000,00 1.100.000,00
5 Pasang Plafond Gypsum+GRC 204,80 m2 DIHITUNG 104.897,78 21.483.065,34
6 Pasang Lis Plafond Gypsum 366,00 m' SNI-2839.2008.6.8 25.410,00 9.300.060,00
                                                                       JUMLAH A.III.d 44.695.625,34               762.791.466,58
e. PEKERJAAN SANITASI DAN PLUMBING LANTAI 1
1 Pasang Instalasi Air Bersih pipa 3/4" AW Wavin 75,00 m' RSNI T-15-2002.6.26 43.922,50 3.294.187,50
2 Pasang Kran Wastafel 3/4 4,00 set RSNI T-15-2002.6.35 131.825,00 527.300,00
3 Pasang Shower KM 4,00 set Taksir 225.000,00 900.000,00
4 Pasang Kran 3/4 8,00 set RSNI T-15-2002.6.35 131.825,00 1.054.600,00
5 Pasang Instalasi Air Kotor Pipa Pralon 3", Wavin Type D 80,00 m' RSNI-15-2002.6.31 56.512,50 4.521.000,00
6 Pasang Instalasi Air Kotor Pipa Pralon 4", Wavin Type D 66,00 m' RSNI-15-2002.6.32 64.075,00 4.228.950,00
7 Pasang Wastafel + Assesoris 4,00 set RSNI-15-2002.6.5 679.050,00 2.716.200,00
8 Pasang Closet Monoblok 2,00 set RSNI-15-2002.6.1 2.616.275,00 5.232.550,00
9 Pasang Septictank Biofil setara Biotank 1,00 set Taksir 4.500.000,00 4.500.000,00
10 Pasang Sumur Resapan 2,00 unit RSNI-15-2002.6.33 2.816.240,25 5.632.480,50
11 Pasang Bak kontrol, Pas. Bata 45x45x50 8,00 unit RSNI-15-2002.6.17 495.240,00 3.961.920,00
12 Pasang Kran Angsa Dapur 2,00 set RSNI T-15-2002.6.35 131.825,00 263.650,00
13 Pasang Tandon Air Stainless Exs "Tirta", Kap. 1000 liter 1,00 set Taksir 4.500.000,00 4.500.000,00
14 Pasang Pompa Air, Grundfos + Instalasinya 1,00 set Taksir 3.750.000,00 3.750.000,00
15 Pasang Sumur Air Bersih (Bor) 1,00 unit Taksir 4.500.000,00 4.500.000,00
16 Pasang Saluran Drainase Buis Beton U-20 80,00 m' RSNI-15-2002.6.14 88.906,00 7.112.480,00
                                                             JUMLAH A.III.e 56.695.318,00                          819.486.784,58
f. PASANG KUSEN PINTU+JENDELA KACA LT 1
1 Pasang Kusen Pintu Alumunium coklat4" 57,00 m' SNI-7393-2008.6.11 111.425,00 6.351.225,00
2 Pasang Kusen Jendela Alumunium coklat 4" 84,00 m' SNI-7393-2008.6.11 111.425,00 9.359.700,00
3 Pasang Pintu Tempered (utama) 4,20 m2 SNI-PtT-30-2000.C.6.16 2.597.110,00 10.907.862,00
4 Pasang Pintu Tempered (samping) 6,30 m2 Ls 2.450.000,00 15.435.000,00
5 Pasang Pintu Frame + isi Multiplek (Gudang+Sekretariat) 6,30 m2 SNI-7393-2008.6.13.a 1.096.355,00 6.907.036,50
6 Pasang Daun Pintu KM Frame Alumunium Stripe, lebar 80 cm 5,88 m2 SNI-7393-2008.6.12 1.746.725,00 10.270.743,00
7 Pasang Daun Jendela casement isi Kaca Bening 5 mm 25,20 m2 Ls 385.000,00 9.702.000,00
8 Pasang Kaca Mati 5 mm 8,40 m2 SNI-PtT-30-2000.C.6.13 149.610,00 1.256.724,00
9 Pasang Kaca Mati 12 mm (diatas pintu utama) 1,00 m2 SNI-PtT-30-2000.C.6.13 2.597.110,00 2.597.110,00
10 Pasang Kaca Bening 8 mm Bavel 21,60 m2 Ls 295.000,00 6.372.000,00
11 Pasang Kaca Grafir diatas jendela) 2,25 m2 Ls 650.000,00 1.462.500,00
12 Pasang Glass Block 64,00 buah Ls 22.000,00 1.408.000,00
                                                                      JUMLAH A.III.f 82.029.900,50                  901.516.685,08
g. PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Pasang kunci tanam biasa 6,00 set SNI-PtT-30-2000.C.6.2 274.250,00 1.645.500,00
2 Pasang engsel pintu 12,00 set SNI-PtT-30-2000.C.6.5 89.250,00 1.071.000,00
3 Pasang engsel jendela 24,00 set SNI-PtT-30-2000.C.6.8 51.250,00 1.230.000,00
4 Pasang Engsel Tanam Dorma Pintu Tempered 6,00 set Taksir 1.575.000,00 9.450.000,00
5 Memasang Doorcloser 6,00 set SNI-PtT-30-2000.C.6.12 788.710,00 4.732.260,00
6 Memasang Rel Jendela Sliding dorong 12,00 set SNI-PtT-30-2000.C.6.12 396.410,00 4.756.920,00
7 Memasang Kunci Pintu Tempered 3,00 set Taksir 450.000,00 1.350.000,00
                                                                   JUMLAH A.III.g 24.235.680,00                    925.752.365,08
h. PEKERJAAN PELENGKAP DAN LAIN-LAIN DI LANTAI-1
1 Pekerjaan Pagar Railling Tangga+pagar Serambi 70,70 m' Taksir 450.000,00 31.815.000,00
2 Pekerjaan Atap Polycarbonat Rangka Pipa diatas Tangga 11,00 m2 Taksir 611.500,00 6.726.500,00
                                                                               JUMLAH A.III.g 38.541.500,00        964.293.865,08
                                                                               JUMLAH LANTAI -                       1 964.293.865,08
B. LINGKUP PEKERJAAN LANTAI-2
B.I. PEKERJAAN PERSIAPAN
1 Pengukuran, Uitzet / bouwplank 163,60 m' LS 12.500,00 2.045.000,00
                                                                               JUMLAH B. I 2.045.000,00                   2.045.000,00
B.II. PEKERJAAN STRUKTUR
a. PEKERJAAN PASANGAN di LANTAI-2
1 Pasangan Bata 1/2 Batu, camp. 1Pc : 5 Ps 296,16 m2 SNI-6897-2008. 6.10 90.259,00 26.731.105,44
2 Plesteran Dinding camp. 1Pc : 5 Ps 640,32 m2 SNI-2837-2008. 6.5 33.785,00 21.633.211,20
3 Plesteran Beton camp. 1 Pc : 3 Ps 650,80 m2 SNI-2837-2008. 6.3 37.238,00 24.234.527,64
4 Pekerjaan Acian Dinding dan Beton 1.291,12 m2 SNI-2837-2008. 6.27 21.162,00 27.322.702,60
5 Pekerjaan Sponengan Sudut 1.968,16 m' SNI-2837-2008. 6.20 8.695,00 17.113.151,20
                                                                                JUMLAH B.II.a 117.034.698,08       119.079.698,08
b. PEKERJAAN BETON di LANTAI - 2
1 Cor Beton kolom struktur K1 30x30
    a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 7,92 m3 SNI-7394-2008 6.8    
       903.815,00 7.158.214,80
    b Pembesian kolom 1.142,33 kg SNI-7394-2008 6.17 10.720,50 12.246.349,97
    c Begesting kolom 2 x pakai 105,60 m2 SNI-7394-2008 6.22 65.883,75 6.957.324,00
2 Cor Beton kolom struktur K2 20x20
    a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 2,88 m3 SNI-7394-2008 6.8
       903.815,00 2.602.987,20
    b Pembesian kolom 451,65 kg SNI-7394-2008 6.17 10.720,50 4.841.891,31
    c Begesting kolom 2 x pakai 57,60 m2 SNI-7394-2008 6.22 65.883,75 3.794.904,00
3 Cor Beton balok struktur B1 20x35
    a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 8,69 m3 SNI-7394-2008.6.8
       903.815,00 7.857.767,61
    b Pembesian Balok 2.130,18 kg SNI-7394-2008 6.17 10.720,50 22.836.627,70
    c Begesting Balok 2 x pakai 83,20 m2 SNI-7394-2008.6.23a 131.767,50 10.963.583,07
4 Cor Beton balok struktur B2 15x30
    a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 1,62 m3 SNI-7394-2008.6.8
       903.815,00 1.464.180,30
     b Pembesian Balok 356,92 kg SNI-7394-2008 6.17 10.720,50 3.826.402,76
     c Begesting Balok 2 x pakai 18,36 m2 SNI-7394-2008.6.23a 131.767,50 2.419.251,30
5 Cor Beton Plat Atap/Dag Talang, tebal 10 cm
     a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 3,42 m3 SNI-7394-2008.6.8
        903.815,00 3.091.047,30
      b Pembesian Plat Atap 1.145,80 kg SNI-7394-2008 6.17 10.720,50 12.283.572,91
      c Begesting Plat Atap 2 x pakai 66,00 m2 SNI-7394-2008.6.24a 161.767,50 10.676.655,00
6 Cor Beton Luisplank Lantai-2, 10x50
      a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 2,30 m3 SNI-7394-2008.6.8
         903.815,00 2.078.774,50
      b Pembesian Luisplank 399,29 kg SNI-7394-2008 6.17 10.720,50 4.280.639,05
      c Begesting Luisplank 2 x pakai 23,00 m2 SNI-7394-2008.6.24a 161.767,50 3.720.652,50
7 Cor Beton Balok Latae 15x20
      a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 3,62 m3 SNI-7394-2008. 6.8    
         903.815,00 3.268.375,80
       b Pembesian Balok Latae 385,57 kg SNI-7394-2008 6.17 10.720,50 4.133.492,08
       c Begesting Balok 2 x pakai 72,60 m2 SNI-7394-2008.6.23a 131.767,50 9.566.320,50
8 Cor Beton Plat canopy (assesories diatas Jendela)
       a Beton mutu fc=19,3 Mpa(K250), slump (12 ± 2)cm, w/c= 0,58 0,64 m3 SNI-7394-2008. 6.8
          903.815,00 578.441,60
       b Pembesian Plat canopy 40,74 kg SNI-7394-2008 6.17 10.720,50 436.735,16
       c Begesting Plat canopy 2 x pakai 16,00 m2 SNI-7394-2008.6.24a 161.767,50 2.588.280,00
                                                      JUMLAH B.II.b 143.672.470,41                              262.752.168,49
B.III. PEKERJAAN PASANGAN ARSITEKTURAL LANTAI-2
a. PEKERJAAN LANTAI di LANTAI-2
1 Urugan Pasir Bawah Lantai, Tebal 7 cm 8,37 m3 SNI-2835-2008. 6.11 80.200,00 671.339,52
2 Pasang Lantai Keramik 60/60, exs Indogress, TPZ, Kw 2 119,58 m2 SNI-7395-2008. 6.9 214.025,00
    25.593.772,98
3 Pasang Dinding Keramik sisi depan 30/50 40,60 m2 SNI-7395-2008. 6.54 184.381,00 7.485.868,60
4 Pasang Dinding Batu Andesit pada Kolom 19,20 m2 Ls 250.000,00 4.800.000,00
                                                            JUMLAH B.III.a 38.550.981,10                         301.303.149,60
b. PEKERJAAN FINISHING CAT LANTAI-2
1 Cat dinding interior setara Jotaplast 645,56 m2 SNI- -2002 6.13 30.155,00 19.466.876,88
2 Cat dinding eksterior setara Jotun weathershield 907,58 m2 SNI -2002 6.13.a 37.355,00 33.902.557,51
3 Cat Plafond Gypsum setara catylac 148,86 m2 SNI -2002 6.15 21.855,00 3.253.403,05
4 Coating batu alam andesit di kolom 19,20 m2 Taksir 55.000,00 1.056.000,00
5 Mengkompon dag beton 27,84 m2 Taksir 37.000,00 1.030.080,00
                                                                JUMLAH B.III.b 58.708.917,44                       360.012.067,04
c. PEKERJAAN LISTRIK/ELECTRICAL LANTAI-2
1 Pasang titik lampu, Kabel 3X2,5 mm, ETERNA 34,00 Titik ELT 6.1 235.900,00 8.020.600,00
2 Pasang Lampu Jari SL 18 watt, OSRAM+Fitting 4,00 Titik Taksir 75.000,00 300.000,00
3 Pasang Lampu Indolite TL 18 x 2 watt TKI 8,00 unit Taksir 387.000,00 3.096.000,00
4 Pasang Lampu Downlight 3" 4,00 unit Taksir 95.000,00 380.000,00
5 Pasang Lampu Tanam di Gapura Pagar 2,00 unit Taksir 350.000,00 700.000,00
6 Pasang Lampu Tempel di Kolom 16,00 unit Taksir 225.000,00 3.600.000,00
7 Pasang Box MCB 6 Ampere 1,00 unit Taksir 1.850.000,00 1.850.000,00
8 Pasang saklar Double, PANASONIC 17,00 unit Taksir 23.000,00 391.000,00
9 Pasang Stop Kontak 300 Watt, PANASONIC 10,00 unit ELT 6.2 232.600,00 2.326.000,00
10 Pasang Lampu Robyong 1,00 unit Taksir 1.250.000,00 1.250.000,00
                                                                  JUMLAH B.III.c 21.913.600,00                     381.925.667,04
d. PEKERJAAN ATAP + PLAFOND di LANTAI-2
1 Pasang rangka atap baja ringan 110,00 m2 Taksir 137.500,00 15.125.000,00
2 Pasang Penutup Atap Genteng Metal Stone Minimalis 132,00 m2 Taksir 122.000,00 16.104.000,00
3 Pasang Nok Metal Minimalis 22,00 m' Taksir 47.500,00 1.045.000,00
4 Pasang Luisplang woodplank 24,00 m' Taksir 55.000,00 1.320.000,00
5 Pasang Plafond Gypsum+GRC 111,36 m2 DIHITUNG 104.897,78 11.681.416,78
6 Pasang Lis Plafond Gypsum 295,60 m' SNI-2839.2008.6.8 25.410,00 7.511.196,00
7 Pasang Kubah Stainless diameter 2 meter (Bangunan Utama) 1,00 unit Taksir 4.500.000,00 4.500.000,00
8 Pasanng Kubah Stainless diameter 1 meter (menara) 4,00 unit Taksir 750.000,00 3.000.000,00
                                                                          JUMLAH B.III.d 60.286.612,78           442.212.279,82
e. PEKERJAAN SANITASI DAN PLUMBING LANTAI-2
1 Pasang Instalasi Air Hujan Pipa Pralon 3", Wavin Type D 48,00 m' RSNI-15-2002.6.31 56.512,50 2.712.600,00
2 Pasang Instalasi Air Hujan Pipa Pralon 4", Wavin Type D 48,00 m' RSNI-15-2002.6.32 64.075,00 3.075.600,00
                                                                           JUMLAH B.III.e 5.788.200,00              448.000.479,82
f. PASANG KUSEN PINTU+JENDELA KACA LANTAI-2
1 Pasang Kusen Pintu Alumunium coklat 4" 18,40 m' SNI-7393-2008.6.11 111.425,00 2.050.220,00
2 Pasang Kusen Jendela Alumunium coklat 4" 126,00 m' SNI-7393-2008.6.11 111.425,00 14.039.550,00
3 Pasang Daun Pintu Frame Alumunium + isi kaca 6,30 m2 SNI-7393-2008.6.13.a 1.147.075,00 7.226.572,50
4 Pasang Daun Jendela casement isi Kaca Bening 5 mm 37,80 m2 Ls 385.000,00 14.553.000,00
5 Pasang Kaca Mati 5 mm 8,40 m2 SNI-PtT-30-2000.C.6.13 149.610,00 1.256.724,00
6 Pasang Kusen Bovenlight+kaca Mati 2,00 m2 Taksir 350.000,00 700.000,00
7 Pasang Kaca Grafir diatas jendela) 3,38 m2 Ls 650.000,00 2.193.750,00
8 Pasang Glass Block 64,00 buah Ls 22.000,00 1.408.000,00
                                                                                JUMLAH B.III.f 43.427.816,50        491.428.296,32
g. PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Pasang kunci tanam biasa 2,00 set SNI-PtT-30-2000.C.6.2 274.250,00 548.500,00
2 Pasang engsel pintu 8,00 set SNI-PtT-30-2000.C.6.5 89.250,00 714.000,00
3 Pasang engsel jendela 24,00 set SNI-PtT-30-2000.C.6.8 51.250,00 1.230.000,00
4 Memasang Doorcloser 4,00 set SNI-PtT-30-2000.C.6.12 788.710,00 3.154.840,00
5 Memasang Rel Jendela Sliding dorong 12,00 set SNI-PtT-30-2000.C.6.12 396.410,00 4.756.920,00
JUMLAH B.III.g 10.404.260,00 501.832.556,32
h. PEKERJAAN PELENGKAP DAN LAIN-LAIN DI LANTAI-2
1 Pekerjaan Ornamen di sekitar Kubah utama+menara 1,00 m' Ls 10.500.000,00 10.500.000,00
2 Pekerjaan Atap Polycarbonat Rangka Pipa diatas Tangga 16,50 m2 Taksir 611.500,00 10.089.750,00
                                                                      JUMLAH B.III.g 20.589.750,00                522.422.306,32
                                                                      JUMLAH LANTAI-2                                 522.422.306,32
                                                      JUMLAH TOTAL LANTAI-1 + LANTAI-2          1.486.716.171,40


                                                                                                                      Sleman, 12 September 2013
                                                                                              Panitia Pembangunan Masjid Al-Amin Pedak